We joined Nord-Stream 2 AG in Zug
Involved on Nord-Stream 1 + Nord-Stream 2 ... that's a total of about 1000 Eiffel Towers that we will deliver on schedule to the pipelay barges.
"GIRLAND": inauguration day in Lussagnet (F.40)
"Pipe On Track" wishes you a Happy New Year
MiniTransat 2013 | "Pas de futur sans numérique"behind Ian Lipinski | "Pipe on Track" is on board !
Double page in "Supply Chain Magazine"
An interesting article on "Big Projects" in "Supply Chain Magazine", of last June. Our participation to the Nord-Stream
project is described page 40 & 41 of this specialized french magazine, which is also available on line :
Supply Chain Magazine #65 or PDF file
Last pipe delivered on schedule to Nord Stream
Slite (Sweden) 14/04/12 : Eupec delivered the last pipe of the
Nord Stream project slightly ahead of schedule despite 2 month of laying
disruption due to bad weather on the Baltic sea. As Planning Manager of this great project for Eupec, I am proud of this wonderful team success.
- April 2012 Last pipe for the project delivered to Saïpem Castoro Sei Laying Barge on schedule
Pipe On Track is working with SICIM for TIGF
Pipe On Track is in charge of the planning for Sicim France, on the TIGF projects : "Artère de Béarn" - a 60 km onshore pipeline between Lacq (64/France) & Lussagnet (40/France) & "GIRLAND" - 60 km furter North. We will manage the planning with MS Project & TILOS for the linear planning, and will implement a dedicated extranet for the project team + different web-mapping tools.
Last pipe coated on schedule for Nord Stream
Mukran (Germany) 11/11/11 : Eupec concrete weight coated on
Schedule the last pipe of the € 7.4 billion Nord
Stream Project : 2450 km 48" offshore pipeline to be laid on the Baltic sea bed, from Vyborg (Russia) to Lubmin (Germany).
Philippe Cattelain (Pipe On Track) was Planning Manager of the Project for Eupec since April 2008 ...
- October 2011 Last pipe for the project delivered from Europipe Mülheim, on schedule
- September 2011 First gas coming through Line 1, from Russia to Germany, on schedule
- May 2011 Nord Stream laid last pipe of first gas pipeline, on schedule
- April 2011 First 2000 km concrete weight coated, on schedule
- May 2010 First 1000 km concrete weight coated, on schedule
- March 2010 First pipe loaded out towards the lay barge, on schedule
- November 2009 start of production in Kotka (Finland), on schedule
- March 2009 start of production in Mukran (Germany), on schedule
- November 2008 start of concrete plant construction in Kotka (Finland), on schedule
- May 2008 start of concrete plant construction in Mukran (Germany), first pipe delivered
Congratulations from French President
Nicolas Sarkozy, French President, while visiting the Dunkerque area, was informed that a small french company was performing on the Nord Stream Project in the Baltic sea. He sent his congratulations to the project team, through Philippe Cattelain (Pipe On Track).